Huntsville, Alabama
Redstone Arsenal
Selective open-air structural demolition of 330' Saturn V test stand with 100% tie-off of personnel and tools.
Project Details
- Location
- Huntsville, AL
- Owner
- Blue Origin
- GC
- Clayco
- Delivery Method
- Subcontractor
- Contract Value
- $1.6 million
- Start Date
- November 2019
- Completion Date
- February 2020
- Total Hours Worked
- 3770
- Recycling Rate
- 99