Indianapolis, Indiana
Gainbridge Fieldhouse
Downtown NBA arena renovation during three off-seasons, including restricted-access structural demolition in tight spaces.
Project Details
- Location
- Indianapolis, IN
- Owner
- Captial Improvement Board of Managers of Marion County
- GC
- Shiel Sexton and JC Ripberger
- Size ft2
- 20,000
- Delivery Method
- Subcontractor (Phase 1), Prime contractor (Phases 2 and 3)
- Contract Value
- $10.6 million
- Start Date
- February 2020
- Completion Date
- July 2022
- Total Hours Worked
- 64000